Environment Ministry v PT North Sumatera Hydro Energy

Case status Settled in court

Latest event: Payments reported, amount not stated (4 Aug 2026 (report date)).

Case details

What the case is about
Floods and landslides
Case outcome
Settled in court
What the court ordered

The court approved a settlement (akta perdamaian, a settlement deed with the force of a final judgment) and ordered both sides to comply with it. The register does not publish the settlement terms.

No money award on record.

1 source
Final
Not confirmed
Open questions

One of six suits the environment ministry filed in January 2026 after the late-2025 floods and landslides in the Batang Toru and Garoga river basins of North Sumatra. The court registers show six separate lawsuits, one per company: two at the Medan District Court, three at the South Jakarta District Court and one at the Central Jakarta District Court. The ministry sued the developer of the Batang Toru hydropower plant. The court approved a settlement on 26 May 2026. A ministry official later said the company had paid, but no amount or receipt has been published.

Province
Sumatera Utara
Claimant
Kementerian Lingkungan Hidup/Badan Pengendalian Lingkungan Hidup
Defendant or respondent
PT North Sumatera Hydro Energy
Who sued whom
Government → company
Legal route
Civil environmental enforcement
Court
PN Jakarta Selatan
Registered with the court (as reported)
20 Jan 2026

Case register entry — Environment Ministry v PT North Sumatera Hydro Energy (trial docket 60/Pdt.Sus-LH/2026/PN JKT.SEL) (Court enforcement register (SIPP))South Jakarta District Court (Pengadilan Negeri South Jakarta)

Case numbers
First instance: 60/Pdt.Sus-LH/2026/PN JKT.SEL
Jurisdiction
Indonesia
Activity since 2010
View dated activity
Record confidence
Not yet ratedWhat this means

Interim measures and immediate enforcement

The ministry asked the court to halt the hydropower project before judgment. No ruling on that request is recorded, and the case ended in a court-approved settlement.

Interim orderProvisi: a temporary order while the case runs, such as stopping work on the damaged land.

Asked for, no ruling yet

Asked for: Order NSHE to stop all work on the Batang Toru hydropower project until final judgment.

Details and sources

Sources
Digugat Rp200 Miliar, PLTA Batang Toru Berpeluang Jalan Lagi lewat Koreksi Total (News report)KatadataGugatan Ganti Rugi Bencana Sumatra: Dua Perusahaan Berdamai, Empat Lanjut Sidang (News report)Katadata

The reported settlement
  • Katadata reported in Aug 2026 that the case ended in a court-approved settlement after mediation, and that the company paid and is carrying out restoration.
The stop-work request
The claim text was not available, so the stop-work request is known only from a news report. It is unknown whether the settlement dealt with it.

Steps on record

“Paid” means a cited source reports the payment; receipts have not been checked independently. A missing record does not mean the company failed to comply.

  1. Step 1: Filing and rulings

    Settled in court
    Case number and source

    Source excerpt

    60/Pdt.Sus-LH/2026/PN JKT.SEL

    Case register entry — Environment Ministry v PT North Sumatera Hydro Energy (trial docket 60/Pdt.Sus-LH/2026/PN JKT.SEL) (Court enforcement register (SIPP))South Jakarta District Court (Pengadilan Negeri South Jakarta)

    20 Jan 2026
    Case registered

    The ministry’s claim was registered at the South Jakarta District Court. It asked for Rp200.69 billion in compensation to the state treasury, plus restoration of the company’s operating area at its own cost under ministry supervision.

    Source excerpt and citation
    sebesar Rp200.688.429.135,- (dua ratus miliar enam ratus delapan puluh delapan juta empat ratus dua puluh sembilan ribu seratus tiga puluh lima rupiah)
    English translationin the amount of Rp200.688.429.135,- (two hundred billion six hundred eighty-eight million four hundred twenty-nine thousand one hundred thirty-five rupiah)

    Case register entry — Environment Ministry v PT North Sumatera Hydro Energy (trial docket 60/Pdt.Sus-LH/2026/PN JKT.SEL) (Court enforcement register (SIPP))South Jakarta District Court (Pengadilan Negeri South Jakarta)

  2. Step 2: Final judgment and review

    No dated event on record for this stage.

  3. Step 3: Enforcement

    26 May 2026
    Settlement or agreement reported

    The court approved a settlement reached in mediation and ordered both parties to comply. The register records no amount; the settlement terms are not public.

    Source excerpt and citation
    Status Putusan | Perdamaian |
    English translationJudgment Status | Settlement |

    Judgment record — Environment Ministry v PT North Sumatera Hydro Energy (trial docket 60/Pdt.Sus-LH/2026/PN JKT.SEL) (Court enforcement register (SIPP))South Jakarta District Court (Pengadilan Negeri South Jakarta)

  4. Step 4: Payment

    4 Aug 2026 (report date)
    Payments reported, amount not stated

    A ministry official told Katadata the company had paid compensation and was carrying out restoration, and that the settlements matched the claims. No amount, date or receipt was given, so no payment is counted.

    Publication date of the Katadata article; the payment date is not reported.

    Source excerpt and citation
    NSHE disebut sudah membayar ganti rugi dan sedang memproses pemulihan lingkungan.
    English translationNSHE is said to have paid damages and to be in the process of carrying out environmental restoration.

    Gugatan Ganti Rugi Bencana Sumatra: Dua Perusahaan Berdamai, Empat Lanjut SidangKatadata

  5. Step 5: Restoration and other orders

    Nothing on record yet.