Environment Ministry v PT North Sumatera Hydro Energy
Case details
- What the case is about
- Floods and landslides
- Case outcome
- Settled in court
- What the court ordered
The court approved a settlement (akta perdamaian, a settlement deed with the force of a final judgment) and ordered both sides to comply with it. The register does not publish the settlement terms.
No money award on record.
1 source
- Judgment record — Environment Ministry v PT North Sumatera Hydro Energy (trial docket 60/Pdt.Sus-LH/2026/PN JKT.SEL) (Court enforcement register (SIPP))South Jakarta District Court (Pengadilan Negeri South Jakarta)
- Final
- Not confirmed
- Open questions
One of six suits the environment ministry filed in January 2026 after the late-2025 floods and landslides in the Batang Toru and Garoga river basins of North Sumatra. The court registers show six separate lawsuits, one per company: two at the Medan District Court, three at the South Jakarta District Court and one at the Central Jakarta District Court. The ministry sued the developer of the Batang Toru hydropower plant. The court approved a settlement on 26 May 2026. A ministry official later said the company had paid, but no amount or receipt has been published.
- Province
- Sumatera Utara
- Claimant
- Kementerian Lingkungan Hidup/Badan Pengendalian Lingkungan Hidup
- Defendant or respondent
- PT North Sumatera Hydro Energy
- Who sued whom
- Government → company
- Legal route
- Civil environmental enforcement
- Court
- PN Jakarta Selatan
- Registered with the court (as reported)
- 20 Jan 2026
Case register entry — Environment Ministry v PT North Sumatera Hydro Energy (trial docket 60/Pdt.Sus-LH/2026/PN JKT.SEL) (Court enforcement register (SIPP))South Jakarta District Court (Pengadilan Negeri South Jakarta)
- Case numbers
- First instance: 60/Pdt.Sus-LH/2026/PN JKT.SEL
- Jurisdiction
- Indonesia
- Activity since 2010
View dated activity
- 20 Jan 2026, Case registered
Case register entry — Environment Ministry v PT North Sumatera Hydro Energy (trial docket 60/Pdt.Sus-LH/2026/PN JKT.SEL) (Court enforcement register (SIPP))South Jakarta District Court (Pengadilan Negeri South Jakarta)
- 26 May 2026, Settlement or agreement reported
Judgment record — Environment Ministry v PT North Sumatera Hydro Energy (trial docket 60/Pdt.Sus-LH/2026/PN JKT.SEL) (Court enforcement register (SIPP))South Jakarta District Court (Pengadilan Negeri South Jakarta)
- 4 Aug 2026 (report date), Payments reported, amount not stated
Gugatan Ganti Rugi Bencana Sumatra: Dua Perusahaan Berdamai, Empat Lanjut Sidang (News report)Katadata
- 20 Jan 2026, Case registered
- Record confidence
- Not yet ratedWhat this means
- Case sources
5 sources
- Case register entry — Environment Ministry v PT North Sumatera Hydro Energy (trial docket 60/Pdt.Sus-LH/2026/PN JKT.SEL) (Court enforcement register (SIPP))South Jakarta District Court (Pengadilan Negeri South Jakarta)
- Negara Gugat Enam Perusahaan Perusak Lingkungan Di Sumatera Utara Rp4,84 Triliun, Menteri LH: Tidak Ada Toleransi Bagi Perusak Lingkungan (Ministry statement)Kementerian Lingkungan Hidup / Badan Pengendalian Lingkungan Hidup
- Judgment record — Environment Ministry v PT North Sumatera Hydro Energy (trial docket 60/Pdt.Sus-LH/2026/PN JKT.SEL) (Court enforcement register (SIPP))South Jakarta District Court (Pengadilan Negeri South Jakarta)
- Gugatan Ganti Rugi Bencana Sumatra: Dua Perusahaan Berdamai, Empat Lanjut Sidang (News report)Katadata
- Digugat Rp200 Miliar, PLTA Batang Toru Berpeluang Jalan Lagi lewat Koreksi Total (News report)Katadata
Interim measures and immediate enforcement
The ministry asked the court to halt the hydropower project before judgment. No ruling on that request is recorded, and the case ended in a court-approved settlement.
- Interim orderProvisi: a temporary order while the case runs, such as stopping work on the damaged land.
Asked for, no ruling yet
Asked for: Order NSHE to stop all work on the Batang Toru hydropower project until final judgment.
Details and sources
Sources
Digugat Rp200 Miliar, PLTA Batang Toru Berpeluang Jalan Lagi lewat Koreksi Total (News report)KatadataGugatan Ganti Rugi Bencana Sumatra: Dua Perusahaan Berdamai, Empat Lanjut Sidang (News report)Katadata- The reported settlement
- Katadata reported in Aug 2026 that the case ended in a court-approved settlement after mediation, and that the company paid and is carrying out restoration.
- The stop-work request
- The claim text was not available, so the stop-work request is known only from a news report. It is unknown whether the settlement dealt with it.
Steps on record
“Paid” means a cited source reports the payment; receipts have not been checked independently. A missing record does not mean the company failed to comply.
-
Step 1: Filing and rulings
Settled in courtCase number and source
Source excerpt
60/Pdt.Sus-LH/2026/PN JKT.SEL
Case register entry — Environment Ministry v PT North Sumatera Hydro Energy (trial docket 60/Pdt.Sus-LH/2026/PN JKT.SEL) (Court enforcement register (SIPP))South Jakarta District Court (Pengadilan Negeri South Jakarta)
20 Jan 2026
Case registeredThe ministry’s claim was registered at the South Jakarta District Court. It asked for Rp200.69 billion in compensation to the state treasury, plus restoration of the company’s operating area at its own cost under ministry supervision.
Source excerpt and citation
sebesar Rp200.688.429.135,- (dua ratus miliar enam ratus delapan puluh delapan juta empat ratus dua puluh sembilan ribu seratus tiga puluh lima rupiah)
English translationin the amount of Rp200.688.429.135,- (two hundred billion six hundred eighty-eight million four hundred twenty-nine thousand one hundred thirty-five rupiah) Case register entry — Environment Ministry v PT North Sumatera Hydro Energy (trial docket 60/Pdt.Sus-LH/2026/PN JKT.SEL) (Court enforcement register (SIPP))South Jakarta District Court (Pengadilan Negeri South Jakarta)
-
Step 2: Final judgment and review
No dated event on record for this stage.
-
Step 3: Enforcement
26 May 2026
Settlement or agreement reportedThe court approved a settlement reached in mediation and ordered both parties to comply. The register records no amount; the settlement terms are not public.
Source excerpt and citation
Status Putusan | Perdamaian |
English translationJudgment Status | Settlement | Judgment record — Environment Ministry v PT North Sumatera Hydro Energy (trial docket 60/Pdt.Sus-LH/2026/PN JKT.SEL) (Court enforcement register (SIPP))South Jakarta District Court (Pengadilan Negeri South Jakarta)
-
Step 4: Payment
4 Aug 2026 (report date)
Payments reported, amount not statedA ministry official told Katadata the company had paid compensation and was carrying out restoration, and that the settlements matched the claims. No amount, date or receipt was given, so no payment is counted.
Publication date of the Katadata article; the payment date is not reported.
Source excerpt and citation
NSHE disebut sudah membayar ganti rugi dan sedang memproses pemulihan lingkungan.
English translationNSHE is said to have paid damages and to be in the process of carrying out environmental restoration. Gugatan Ganti Rugi Bencana Sumatra: Dua Perusahaan Berdamai, Empat Lanjut SidangKatadata
-
Step 5: Restoration and other orders
Nothing on record yet.