From Ruling to Remedy

Celukan Bawang residents and Greenpeace v Governor of Bali

Case status Claim rejected or overturned

Latest event: First-instance decision (Aug 2018 (day unknown)).

Case details

What the case is about
Coal mining and coal power · Climate change
Case outcome
Claim rejected or overturned
What the court ordered
  • No court source confirms a remedy.
  • Claim rejected at first instance (2018). The rejection was upheld by the Surabaya Administrative High Court, on cassation (224 K/TUN/LH/2019) and on judicial review (67 PK/TUN/LH/2020). No remedy was awarded.

No money award on record.

2 sources
Final
Yes
Open questions

The challenge failed at every stage, according to the Sabin Center climate litigation database. Sources describe the first-instance grounds differently: the Sabin Center says procedural, while the Jakarta Post reports that the court found the plaintiffs' arguments unsupported by scientific evidence. The appeal, cassation and judicial-review decision dates have not been obtained.

Sources disagree on some details. The reported amounts and the summaries of each court stage still need review.

Province
Bali
Claimant
I Ketut Mangku Wijana, dkk; Greenpeace Indonesia
Defendant or respondent
Gubernur Bali
Other parties
Who sued whom
People / NGOs → state and company
Legal route
Administrative permit challenge
Court
PTUN Denpasar
Case numbers
First instance: 2/G/LH/2018/PTUN.DPS
Appeal: 221/B/LH/2018/PT.TUN.SBY
Cassation: 224 K/TUN/LH/2019
Judicial review (PK): 67 PK/TUN/LH/2020
Jurisdiction
Indonesia
Activity since 2010
View dated activity
Record confidence
Not yet ratedWhat this means

Interim measures and immediate enforcement

The residents and Greenpeace asked for the power plant permit to be suspended. The administrative court refused, and the appeal court upheld that without discussing it after ruling the claim was filed too late.

Permit suspensionPenundaan: the administrative court suspends the challenged permit while the case runs.

Asked for, not granted

Asked for: Suspend the Bali Governor's environmental permit (SK 660.3/3985/IV-A/DISMPT, 28 April 2017) for the Celukan Bawang coal power plant expansion until final judgment.

How each court ruled and sources
  1. Administrative court, 16 Aug 2018: turned it downThe reasons are unavailable, but the court threw out the claim because the plaintiffs lacked standing.
  2. Administrative appeal court, 26 Dec 2018: turned it downThe appeal court upheld the dismissal, finding the claim was filed too late, and did not discuss the suspension.

Sources
Administrative appeal court judgment, 26 Dec 2018 — 221/B/LH/2018/PT.TUN.SBY. — Celukan Bawang residents and Greenpeace v Governor of Bali (Court judgment)Supreme Court of the Republic of Indonesia

The renewed suspension request
  • The plaintiffs asked again for the suspension on appeal.
The trial court’s reasons
The administrative court judgment was not available, so its reasons for refusing the suspension are unknown. The Supreme Court rulings were also unavailable, so it is unknown whether they revisited it.

Steps on record

“Paid” means a cited source reports the payment; receipts have not been checked independently. A missing record does not mean the company failed to comply.

  1. Step 1: Filing and rulings

    Aug 2018 (day unknown)
    First-instance decision

    Denpasar Administrative Court rejected the challenge to the environmental permit.

    The Jakarta Post reported on 17 August 2018 that the court ruled "on Thursday"; the exact day is not taken from the judgment.

    Source excerpt and citation

    Source excerpt in English

    In a ruling that dashed the hopes of local residents and activists wanting to stop the expansion, the court declared on Thursday that the expansion plan posed no threat to the environment, nor did it put at risk the livelihoods of local farmers and fishermen.

    Court rejects lawsuit challenging Buleleng power plant projectThe Jakarta Post

  2. Step 2: Final judgment and review

    Final judgment reported (date not recorded)

    An academic bibliography lists the Celukan Bawang case at three court stages without giving the outcomes.

    Source excerpt and citation
    PTUN Denpasar (2018), Putusan Nomor 2/G/LH/2018/PTUN.DPS, I Ketut Mangku Wijana, dkk dan Greenpeace Indonesia v. Gubernur Bali dan PT. PLTU Celukan Bawang . PTTUN Surabaya (2018), Putusan Banding Nomor 221/8 /LH/2018/PT.TUN.SBY., I Ketut Mangku Wijana, dkk dan Greenpeace Indonesia v. Gubernur Bali dan PT. PLTU Celukan Bawang . Mahkamah Agung (2019), Putusan Kasasi Nomor 224 K/TUN/LH/2019, I Ketut Mangku Wijana, dkk dan Greenpeace Indonesia v. Gubernur Bali dan PT. PLTU Celukan Bawang .
    English translationDenpasar Administrative Court (2018), Judgment Number 2/G/LH/2018/PTUN.DPS, I Ketut Mangku Wijana et al. and Greenpeace Indonesia v. Governor of Bali and PT. PLTU Celukan Bawang . Surabaya Administrative High Court (2018), Appeal Judgment Number 221/8 /LH/2018/PT.TUN.SBY., I Ketut Mangku Wijana et al. and Greenpeace Indonesia v. Governor of Bali and PT. PLTU Celukan Bawang . Supreme Court (2019), Cassation Judgment Number 224 K/TUN/LH/2019, I Ketut Mangku Wijana et al. and Greenpeace Indonesia v. Governor of Bali and PT. PLTU Celukan Bawang .

    Analisis akademik putusan izin lingkungan Celukan Bawang — Andri Gunawan Wibisana dan Fajri Fadhillah (Academic study)Universitas Indonesia

  3. Step 3: Enforcement

    Nothing on record yet.

  4. Step 4: Payment

    Nothing on record yet.

  5. Step 5: Restoration and other orders

    Nothing on record yet.